Home   Gibraltar 1
Summary of March 4, 2004 Zoning Hearing Board Meeting
 
 

Note: The following is not a verbatim transcript of the Zoning Hearing Board meeting; it is simply one person’s summary of the major points made by those involved in the hearing process.  For that reason, quotation marks are not used unless a direct quote was recorded.  For information about obtaining an official ZHB transcript, contact the New Hanover Township office.

The meeting started with the cross-examination of Mr. William Flederbach by township residents and the zoning hearing board members.  Flederbach is the township’s air pollution and meteorology expert. He works for O’Brien and Gere.

Mr. Roger Buchanan, President of Paradise Watchdogs asked Flederbach about projected dust emissions. Flederbach said that much of the dust at 150 micro grams is not visible and that there are no regulations that control invisible emissions.  Flederbach said that 150 micro grams exceeds standards.  But, it’s not standard practice in PA to monitor or enforce invisible dust emissions, even if they cause health problems. He also said that in PA facilities are not required to set up monitoring stations for air quality.

The zoning board asked a few clarification questions.

At this time, Ms. Julie Von Spreckelsen, an associate of Bob Brant, township solicitor, redirected Felderbach.

Von Spreckelsen began with a clarification of the mistake Flederbach made in the numbers on his charts back in January when cross-examined by Mr. Stephen Harris, attorney for Gibraltar Rock, Inc.  The discrepancy was that the charts had 1.5 microgram of particulate/meter2 instead of 1.5 microgram of particulate/centimeter2

Flederbach said that this does not invalidate his data; it actually has no impact on the conclusions.  He then went on to show a number of tables that he created after re-running his mathematical models.  In his tables he used three years of operation:

  • 2004, which was to be the first year of operation (originally Gibraltar Rock thought they were going to have the quarry operating in 2002 and then 2003, then 2004…)

  • 2005, proposed second year of operation

  • 2009, proposed full operation of all three plants (quarry, asphalt, concrete).

The table headings are year of operation and % of standards. % of standards means that if the standard is 1.5 microgram of particulate/centimeter2, then the number listed is either less than or more than the standard. You will see in the tables he presented that most are over the allowable standards.

We will summarize his corrected slides below.

Table 1 – Total Monthly Particulate Matter Deposited on the Land Surrounding the Quarry

Year

% of Standard 

Over or Under Allowable Standard

2004

168%

Over

2005

139%

Over

2009

343%

Over, exceeded standard by 243%

Flederbach also listed that the rate of dust and particulate material emission (See December 9, 2003 summary for definitions of PM (particulate matter), PM10, and PM 2.5

Table 2 – Total Yearly Emissions 

PM10

14.35 tons/year 

PM2

3.85 tons/year 

TSP (total particulate matter, or the total amount of dust---visible and invisible)

46.10 tons/year 

OR, (92,200 pounds of material emitted into the air each year.)

Table 3 – Re-run of model for only proposed quarry south of Hoffmansville Rd.

Year

Amount

Over or Under the Standard (150 micrograms/meter3)

2004

841 micrograms/meter3

Over

2005

1706 micrograms/meter3

Over

2009

3600 micrograms/meter3

Way Over

Table 4 – Comparison of Previous Testing and Modeling Only Land South of Hoffmansville Rd. (This is a look at only one quarry pit, not two.)

Year

Previous Testing

New Testing (only South of Hoffmansville Rd.

2004

841 micrograms/meter3

841 micrograms/meter3

2005

509 micrograms/meter3

1706 micrograms/meter3

2009

1934 micrograms/meter3

3600 micrograms/meter3

Table 5 – Total Monthly Amount of Suspended Particles Coming off Site

Year

% of Standard 

Over or Under the Standard (150 micrograms/meter3)

2004

240%

Over

2005

327%

Over

2009

609%

Over

Table 6 – Comparison of the Results of Deposited Materials

Year

Previous Testing

New Testing (only South of Hoffmansville Rd.

2004

2.5

3.6

2005

2.1

4.9

2009

5.1

9.1

Table 7 – Concentration by Source

Source

2004

2005

2009

Mining

774

1638

3259

Processing Stone

64

95

83

Paved Roads

6

21

34

Concrete Plant

-

-

20

Asphalt Plant

-

-

476

Flederbach then said that his earlier estimates were based on the plants operating 24 hours per day, 7 days a week, 365 days a year. So, he said he re-ran the models using a more normal work schedule.  He used Two shifts a day (16 hours), 7 days a week, but only running the operation during months of good weather (March through November.  After running this he found the following:

Table 8 – Total Amount with More Normal Working Hours

Year

Amount of particulate material

Over or Under the Standard (150 micrograms/meter3)

2004

213 micrograms/meter3

Over

2005

263% micrograms/meter3

Over

2009

851 micrograms/meter3

Over

And finally,

Table 9 – Total Amount Over a 30-day Period (2 shifts/day)

Year

% of Standard 

Over or Under the Standard (150 micrograms/meter3)

2004

154%

Over

2005

213%

Over

2009

460%

Over

Von Spreckelsen ended her redirect of Felderbach. Harris proceeded with a weak re-examination of the redirect; so weak in fact that I didn’t write anything about it.  Ok, maybe it wasn’t so weak as it was getting late.

Ms. Bell, the attorney for the Zoning Hearing Board explained to the residents, board, and attorneys that Von Spreckelsen’s next witness was not permitted. Because of this, the next meeting, April 1, 2004 will be set aside to allow those residents with party status to make statements. 

The next GR 1 meeting is April 1, 2004 at the New Hanover Township Building, 7:00 PM.

 

See Also:
Summary of the previous meeting (February 11, 2004)

This page was last updated March 10,  2004.
Paradise Watch Dogs
BAN the Quarry
P.O. Box 115
Frederick, PA  19435

Please e-mail your comments about this site to the webmaster.